ASPHALT CONCRETE ROADS 34KM
The Rwanda Ministry of infrastructure(MININFRA) represented by the City of Kigali prized NPD LTD with a tender of upgrading 34.628km of existing earth road within different areas in the city of Kigali for a better road network in the city. This project’s execution period was 18 months with a finishing layer made of Asphalt Concrete.
The scope of the work included but not limited to;
• A side walk made of pavers on one side of the road
• A drainage system consisting of pipe and box culverts and a bridge on the other side
• Finishing layer or wearing course made of Asphalt Concrete

IMG_20140313_135538

Compaction test before laying the Asphalt Concrete

IMG_4240

Putting Asphalt Concrete on one of the roads